Government Targets Some New Toll Roads Operated in 2018

14/02/2018

Highway

Jakarta - 25 new toll roads with the total length of 615 Km will be inaugurated in 2018. The total length is not included of 220 Km toll roads that have not finished yet on time.
Head of Public Communication Bureau of the Ministry of Public Works and Housing (PUPR) Endra S Atmawidjaja explains, 69 Km from the total of 615 Km were built using State Budget (APBN) where the rest of 546 Km was not funded by the State Budget.
Beginning from 2015 until the end of 2017, there is already 332,6 Km toll roads has been inaugurated. Head of Toll Road Regulatory Agency (BPJT of the Ministry of Public Works and Housing), Herry Trisaputra Zuna approximates there is 1.851 Km new toll road will be added until the end of 2019.
Here is the schedule of new toll roads that targetted to operate this year:

1. Bakauheni-Terbanggi Besar

A. Bakauheni-Terbanggi Besar1 Segment IC (Bakauheni Harbour-Bakauheni), Lampung (construction year: 2016-2018) length of 8,9 Km (January)
B. Bakauheni-Terbanggi Besar 2 Segment Sidomulyo-Lematang, Lampung (construction year: 2016-2018) length of 5,3 Km (January)
C. Bakauheni-Terbanggi Besar 1 Segment Bakauheni-Sidomulyo, Lampung (construction year: 2016-2018) length of 30,5 Km (June)
D. Bakauheni-Terbanggi Besar 2 Segment Lematang-Kota Baru, Lampung (construction year: 2016-2018) length of 35,48 Km (June)
E. Bakauheni-Terbanggi Besar 3 (Kota Baru-Metro) Lampung (construction year: 2016-2018) length of 29 Km (June)
F. Bakauheni-Terbanggi Besar 4 (Metro-Terbanggi Besar), Lampung (construction year: 2016-2018) length of 31,8 Km (June)

2. Solo-Ngawi

A. Solo-Ngawi JC Kertosuro-SS Solo (Government/State Budget), Central Java construction year: 2013-2018) length of 20,9 Km (March)
B. Solo-Ngawi Section 1 (Solo-Mantingan) Segment Karanganyar-Sragen (construction year: 2013-2018), Central Java with length of 13,8 Km (March)
C. Solo-Ngawi Section 1 (Solo-Mantingan) Segment Sragen-Mantingan (construction year: 2013-2018), Central Java with total length of 21,35 Km (March)
D. Solo-Ngawi Section 2 (Mantingan-Ngawi) (construction year: 2015-2018), Central Java with length of 34,2 Km (March)

3. Ngawi-Kertosono

A. Ngawi-Kertosono Section 1 (Ngawi 1C-Madiun 1C), East Java (construction year: 2015-2018) length of 20 Km (March)
B. Ngawi-Kertosono Section 2 (Madiun 1C-Caruban 1C) East Java (construction year: 2015-2018) length of 8,45 Km (March)
C. Ngawi-Kertosono Section 3 (Caruban 1C-Nganjuk 1C) East Java (construction year: 2015-2018) length of 21,6 Km (March)
D. Ngawi-Kertosono JBH Solo Kertosono (China Government’s Loan) East Java-Central Java (construction year: 2015-2018) length of 37,5 Km (December)

4. Pejagan-Pemalang

A. Pejagan-Pemalang Section 3 (East Brebes- East Tegal) Central Java (construction year: 2015-2018) length of 10,14 Km (March)
B. Pejagan-Pemalang Section 4 (East Tegal-Pemalang), Central Java (construction year: 2015-2018) length of 26,9 Km (March)

5. Cijago

A. Cinere-Jagorawi Section 2 (Bogor Highway-Kukusan), West Java (construction year: 2014-2018) length of 5,5 Km (March)

6. Desari

A. Depok-Antasari Section 1 (Antasari-Brigif/Cinere), Jakarta (construction year: 2014-2018) length of 6,8 Km (April)

7. Palindra

A. Palembang-Indralaya Section 3 (KTM-Simpang Indralaya) (waiting for the section 2 to be operated), South Sumatera (construction year: 2016-2018) length of 9,28 Km (April)
B. Palembang-Indralaya Section 2 (Pamulatan-KTM), South Sumatera (construction year: 2016-2018) length of 4,9 Km (June)

8. Ciawi-Sukabumi

A. Ciawi-Sukabumi Section 1 (Ciawi-Cigombong) Segment Ciawi-Caringin, West Java (construction year: 2015-2018) length of 7,3 Km (April)
B. Ciawi-Sukabumi Section 1 (Ciawi-Cigombong) Segment Caringin-Cigombong, West Java (construction year: 2015-2018) length of 8,05 Km (April)

9. Becakayu

A. Bekasi-Cawang-Kampung Melayu Section 1A (Casablanca-Cipinang) Segment Cipinang-Kebon Nanas, Jakarta (construction year: 2017-2018) length of 1,8 Km (April)
B. Bekasi-Cawang-Kampung Melayu Section 1A (Casablanca-Cipinang) Segment Kebon Nanas-Casablanca, Jakarta (construction year: 2017-2018) length of 2,72 Km (December)

10. MKTT

A. Medan-Kualanamu-Tebing Tinggi (MKTT) Section 1 funded by State Budget (Tanjung Morawa-IC Perbarakan), North Sumatera (construction year: 2015-2018) length of 3,25 Km (April)
B. Medan-Kualanamu-Tebing Tinggi Section 7 (IC Sei Rampah-IC Tebing Tinggi), North Sumatera (construction year: 2017 - 2018 ) length of 9,3 Km (December)

11. Medan-Binjai

A. Medan-Binjai Section 1 (Veteran Road-SS Heltevia), North Sumatera (construction year: 2015-2018) length of 2,8 Km (April)
B. Medan-Binjai Section 1 (Tanjung Mulia-Helvetia), North Sumatera (construction year: 2015-2018) length of 6,27 Km (December)

12. BORR

A. Bogor Ring Road Section 2B (KD Badak-SP Yasmin), West Java (construction year: 2017-2018) length of 2,05 Km (April)

13. Batang-Semarang

A. Batang-Semarang Section 1 (Batang-East Batang), Central Java (construction year:r 2016-2018) length of 3,2 Km (June)
B. Batang-Semarang Section 2 (East Batang-Weleri), Central Java (construction year: 2016 - 2018) length of 36,35 Km (June)
C. Batang-Semarang Section 3 (Weleri-Kendal), Central Java (construction year: 2016-2018) length of 11,05 Km (June)
D. Batang-Semarang Section 4 (Kendal-Kaliwungu), Central Java (construction year: 2016-2018) length of 13,5 Km (June)
E. Batang-Semarang Section 5 (Kaliwungu-Semarang), Central Java (construction year: 2016-2018 ) length of 10,9 Km (June)

14. Kayu Agung-Betung

A. Kayu Agung-Palembang-Betung Section 1 (Kayu Agung-Jakabaring), South Sumatera (construction year: 2016-2018) length of 33,5 Km (June)
B. Kayu Agung-Palembang-Betung Section 2 (Jakabaring-Musi Landas, South Sumatera (construction year: 2016-2018) length of 33,9 Km (September)

15. Terbanggi-Kayu Agung

A. Terbanggi Besar-Kayu Agung Section 1 (Terbanggi Besar-Pematang Panggang), Lampung (construction year: 2017-2018) length of 100 Km (June)
B. Terbanggi Besar-Kayu Agung Section 2 (Pematang Panggang-Kayu Agung), Lampung (construction year: 2017-2018) length of 85 Km (June)

16. Pemalang-Batang

A. Pemalang-Batang Section 1 (Pemalang 1C-Pekalongan 1C), Central Java (construction year: 2016-2018) length of 23,3 Km (July)
B. Pemalang-Batang Section 2 (Pekalongan 1C-Batang 1C), Central Java (theconstruction year 2016-2018) length of 15,9 Km (July)

17. Gempol-Pasuruan

A. Gempol-Pasuruan Section 2 (Rembang-Pasuruan), East Java (construction year: 2015-2018) length of 8,1 Km (August)
B. Gempol-Pasuruan Section 3 (Pasuruan-Grati), East Java (construction year: 2017-2018) length of 12,15 Mm (December)

18. Semarang-Solo

A. Semarang-Solo Section 4 (Salatiga-Boyolali), Central Java (construction year: 2016 - 2018 ) length of 24,13 Km (September)
B. Semarang-Solo Section 5 (Boyolali-Kertosuro), Central Java (construction year: 2016 - 2018) length of 8,41 Km (September)

19. Pasuruan-Probolinggo

A. Pasuruan-Probolinggo Section 1 (Grati-Tongas), East Java (construction year: 2016-2018) length of 7,93 Km (October)
B. Pasuruan-Probolinggo Section 2 (Tongas-West Probolinggo), East Java (construction year: 2016-2018) length of 23,38 Km (October)
C. Pasuruan-Probolinggo Section 3 (West Probolinggo- East Probolinggo), East Java (construction year: 2016-2018) length of 1,08 Km (October)

20. Krian-Manyar

A. Krian-Legundi-Bunder-Manyar Section 1 (Legundi-Kedamean-Menganti), East Java (construction year: 2016-2018) length of 14,7 Km (December)
B. Krian-Legundi-Bunder-Manyar Section 2 (Kedamean/Menganti-Boboh), East Java (construction year: 2016-2018) length of 4,44 Km (December)
C. Krian-Legundi-Bunder-Manyar Section 3 (Boboh-Bunder), East Java (construction year: 2016-2018) length of 10,16 Km (December)

21. Pandaan-Malang

A. Pandaan-Malang Section 1 (SS Pandaan-SS Purwodadi), East Java (construction year: 2016 - 2018 ) length of 18,57 Km (December)
B. Pandaan-Malang Section 2 (SS Purwodadi-SS Lawang), East Java (construction year: 2016-2018) length of 7,74 Km (December)
C. Pandaan-Malang Section 3 (SS Lawang-SS Pakis), East Java (construction year:r 2016-2018) length of 8,32 Km (December)

22. Cisumdawu

A. Cileunyi-Sumedang-Dawuan Section 1 (Cileunyi-Tanjung Sari), West Java (construction year 2015 - 2018 ) length of 12,2 Km (December)
B. Cileunyi-Sumedang-Dawuan Section 2 (Tanjung Sari-Sumedang), West Java (construction year 2015-2018) length of 19,1 Km (December)

23. Pekanbaru-Dumai

A. Pekanbaru-Dumai Section 1 (Pekanbaru-Minas), Riau (construction year 2016-2018) length of 9,2 Km (December)
B. Pekanbaru-Dumai Section 2 (Minas-Petapahan/South Kandis), Riau (2016-2018) length of 23,6 Km (December)

24. Kertosono-Mojokerto

A. Kertosono-Mojokerto Section 4, Central Java-East Java (construction year 2016-2018) (December)

25. Porong-Gempol

A. Porong-Gempol Section Porong-Kejapanan, East Java (construction year 2016-2018) length of 7,05 Km (December).

Sumber: detik.com